鸡西市热力公司与航天部第四总体设计部于86年4月开始研制鸡西市集中供热管网微机监测系统。该系统计划分二期完成,第一期工程建设25个供热分配站和1个监测中心站,第二期工程完成其余27个供热分配站。至87年3日,微机监测系统第一期工程已全部安装、调试完成,并投入了试运行。
The Jixi City Thermal Power Company and the Fourth General Design Department of the Aerospace Department started development of the Jixi City Central Heating Pipe Network microcomputer monitoring system in April, 86. The system is planned to be completed in two phases. The first phase of the project will build 25 heat distribution stations and one monitoring center station, and the second phase will complete the remaining 27 heat distribution stations. As of the 3rd of the 87th, the first phase of the microcomputer monitoring system has been installed and commissioned and put into trial operation.