作为62项援藏项目最大的工程——西藏满拉水利工程,目前截流的各项准备工作,正在紧张筹备之中,待水利部正式批准截流日期后即进行截流。满拉水利枢纽工程,截流方式采用一次拦断河流,隧洞过流。导流洞后半部分与泄洪洞结合,进口高程4190.00m,出口高程4184.5m,总长648.77m 其中专设导流洞长292.6m,段面尺寸7.5×6.3m(宽×高),泄洪洞结合部分长356.17m,段面尺寸7.8m×11.3m(宽×高),形式均为城门洞型。1994年8月25日武警水电第三总队进场进行施
As the 62 largest Tibet-Tibet project - Tibet Manla water conservancy project, the current closure of the preparatory work is under intense preparation until the Ministry of Water Resources formally approved the closure of the closure of the river. Manla water control project, cut off the way used to intercept a river, the tunnel flow. The second half of the diversion tunnel is integrated with the flood discharge tunnel with an elevation of 4190.00m, an elevation of 4184.5m and a total length of 648.77m. The length of the special diversion tunnel is 292.6m and the section size is 7.5 × 6.3m (width × height) Part of the length of 356.17m, section size 7.8m × 11.3m (width × height), the form is the city gate type. On August 25, 1994, the Armed Police Third Hydropower Corps came into operation