本文根据等级航道基础施工干扰大、封航手续审批难、大型船舶设备多等特点,结合跨越国家Ⅰ级航道的某特大桥主跨主墩承台施工,详细阐述了深水基础采用拉森SKSP-Ⅳ型钢板桩、整体钢围囹下沉法施做钢板桩围堰的施工方案及工艺方法。本方法既保证了深水基础施工的结构安全,也极大缩短了工期,解决了高等级航道干扰大、深水基础施工周期长、耗费材料多的难题,可为部分深水基础施工特别是高等级航道内的深水基础及承台墩身施工提供借鉴。
Based on the large construction disturbance of grade waterway, difficulty in approving seal-sealing procedures and the large number of large-scale ships and equipment, combined with the construction of the main pier cap of main span of a super-long bridge spanning the Class I national waterway, this paper elaborates the deepwater foundation with Larsen SKSP- Ⅳ-type steel sheet piles, the whole steel Wai 囹 sink method for the construction of steel sheet cofferdam construction methods and methods. The method not only ensures the structural safety of the deep-water foundation construction but also shortens the construction period greatly. The invention solves the problems of high-grade waterway interference, long construction period of long-water foundation and cost of materials. The method can be used for some deepwater foundation construction, Within the deep-water base and cap pier pier construction to provide reference.