一、工程概况:甲、开工与结工时间:本期工程施工日期原定为三月十号开工,五月二十日结工。由于粮草等准备工作不够,延至二十号开工,以及各地民工路程远近不同(最远曲阜四百里),因之先后开工日期亦不一致,先期开工的只有一个县(于十九日),余继续开工最后东海一县二十七日才开工,致使工程结束产生迟早现象。最早于五月十五日完工,最晚迟至二十三日,施工期间总计雨工七天,休息两天,实际工作不足五十天。乙、参加干部与民工情况:基本参加工作的计干部二四八五人,民工六三,五五三人,属滨海、台枣、沂蒙、尼山四个专区计二十个县,及新海连一个市,共计为十三个指挥所,五八个大队,三一七个中
First, the project profile: A, start and end time: the current construction date originally scheduled for March 10 started, May 20 knot. Due to the lack of preparation work such as forage grass, it was delayed to start on the 20th and the distances traveled by migrant workers in other places were far and away (four hundred miles as far as Qufu). The date of commencement was also inconsistent. Only one county started operation earlier (on the 19th) To continue the construction of the last East China Sea County on the 27th started, resulting in the project sooner or later the end of the phenomenon. The earliest was completed on May 15, the latest as late as 23 days. During the construction period, the total number of rain-makers was seven days and the rest was two days. The actual work was less than 50 days. B. Participation in Cadres and Migrant Workers: The basic cadres and workers participating in the work of 2485, migrant workers in June 3 and May 5, are 20 counties in the four special districts of Binhai, Taiwan, Yimeng and Nishan, and Xinhai Even a city, a total of 13 command posts, five brigades and brigades, 317 in