鞍钢1780mm热轧1997年5月正式破土动工,到1999年5月土建工程基本结束,主轧线设备安装工作也于1999年5月底收尾,从1999年6月1日起主轧线设备全面进入单体调试。根据鞍钢公司的要求,鞍钢1780mm热轧工程轧钢时间从2000年2月1日提前到1999年11月1日。因此,该工程的调试计划要按新的工期安排进行修改和调整。目前,中外双方参与工程建设的技术人员和工人都在为实现新的调试计划目标努力工作,连续作战。我院承担的设计任务早在1998年12月底已经全部如期完成。
1780mm Hot Rolling of Ansteel formally broke ground in May 1997 and by the end of May 1999 the civil works basically ended. The equipment installation of the main rolling mill was also completed by the end of May 1999, and the main rolling mill equipment was fully entered into operation on June 1, 1999 Monomer debugging. According to Anshan Iron and Steel Company’s requirements, Anshan Iron and Steel 1780mm hot rolling rolling time from February 1, 2000 advance to November 1, 1999. Therefore, the project’s commissioning plan to be revised and adjusted according to the new schedule. At present, both technicians and workers participating in the construction of the project both at home and abroad are working hard to achieve the goal of a new commissioning plan and fight continuously. The design tasks undertaken by our hospital have all been completed as scheduled as early as the end of December 1998.