公司转炉厂两台罗可普方坯连铸机分别于1993年12月底及1994年4月中旬热试机成功。投产初期,由于车间布置不顺,基建遗留问题较多,加上生产组织及工艺操作技术不熟练等因素影响,因此,连铸生产不顺,产量上不去。为了发挥方坯连铸机的作用,公司开展了连铸攻关。通过攻关,180×220mm方坯月产量由元月的826吨增加到7月的10345吨。但用于中型厂一火成材、效益较高的120×120mm 小方坯生产仍然不过关。为此,
The company converter plant two Luo Ke Pu billet caster at the end of December 1993 and mid-April 1994 thermal test success. In the initial stage of production, due to the unsmooth workshop layout, more problems left over from infrastructure projects, and the unskilled production organization and technology, the continuous casting production was not smooth and the output did not go up. In order to play the role of billet caster, the company launched a continuous casting research. Through research, monthly production of 180 × 220mm billets increased from 826 tons in January to 10,345 tons in July. But for a medium-sized plant a fire, the benefits of higher 120 × 120mm billet production is still not off. to this end,