我国20万kW机组曾多次发生大轴弯曲事故,弯曲的部位一般都在高压缸进汽侧的高压汽封段,且均由运行中径向磨损所引起。笔者通过通辽、长山电厂4台国产20万kW机组的安装实践,探讨了高、中压转子三支点合理的安装工艺,保证准确的动静径向间隙,以避免或减少汽轮机大轴弯曲事故。一、结构特点与安装要求国产20万kW机组的高、中压转子为三支点结构:高压转子进汽侧通过刚性靠背轴与中压转子相连,与中压转子共用一个支持推力联
China’s 200,000 kW unit has repeatedly occurred in major axis bending accident, the bending parts are generally high-pressure cylinder into the steam side of the high-pressure steam seal, and are caused by radial wear and tear during operation. Through the installation practice of 4 domestic 200,000 kW units in Tongliao and Changshan Power Plant, the author discusses the reasonable installation process of the three fulcrums of high and medium pressure rotors to ensure accurate dynamic and static radial clearance to avoid or reduce the bending accident of steam turbine shaft. First, the structural characteristics and installation requirements Domestic 200,000 kW unit of high and medium pressure rotor for the three-point structure: high-pressure rotor into the steam side of the rigid backrest shaft connected with the medium voltage rotor, and share a support thrust thrust thrust