实物量法编制工程造价在国际上已被普遍采用 ,它与定额法的不同之处 ,就在于它解决了地域差别、创新施工技术与传统技术的差别以及施工方案与标价脱节的矛盾 ,实现了地域、技术与价格的统一。通过黄河下游某堤防加高培厚工程运用实物量法的实例 ,论证了黄河下游基建工程采用实物量法的可行性 ,表明实物量法不仅可以做到“因地制宜”、“量体裁衣” ,更重要的一点是它可以有效地控制工程投资。
The construction cost of physical quantity method has been widely adopted in the world. The difference between it and the quota method lies in that it has solved the problem of geographical difference, the difference between innovative construction technology and traditional technology, and the contradiction between construction plan and standard price, Geography, technology and price unity. Through the example of physical quantity method in a dikes and embankment project in the lower reaches of the Yellow River, the feasibility of using the physical quantity method in the construction of the lower Yellow River is demonstrated. The more important point is that the physical quantity method can not only “adapt to local conditions” and “tailor” It can effectively control the project investment.