摘 要:对工程项目施工阶段的质量控制合理与否直接影响着整个工程质量的好坏,只有采取科学、合理、有效的质量管理和控制措施,才能保证整个工程的施工质量和施工进度。因此,各施工部门或单位一定要培养综合素质较高的复合型人才,同时引进现代化先进的施工技术和施工设备,并根据施工的相关要求进行资源的优化配置,使人力资源、物力资源合理利用,对工程项目的施工前期、施工中期、施工后期进行全程的质量管理和控制,在保证施工质量的基础上,努力获取最大的经济效益,为国家和人民创造更多的社会效益。
关键词:工程施工;质量控制;措施Abstract: The stage of construction project quality control is reasonable or not directly affects the entire project quality is good or bad, only to take the quality management and control measures of scientific, reasonable, effective, in order to ensure the construction quality and the construction progress of the whole project. Therefore, the construction of composite personnel departments or units must cultivate the high comprehensive quality, at the same time, the introduction of modern advanced construction technology and construction equipment, optimize the allocation of resources in accordance with the relevant requirements and construction, make rational use of human resources, material resources, the construction of the project early, middle, late construction construction quality management and control of the whole, to ensure construction quality, strive to obtain the maximum economic benefits, creating more social benefit for the country and people.
Keywords: engineering construction; quality control; measures
中图分类号:TU71
1具体工程举例
现以某一分别由一桩14层的办公楼和一桩12层的单人居住楼房两部分组成办公楼工程项目为例进行分析。
该办公楼的工程要求如下:办公楼的高度由建筑高度60m和顶层钢桅杆高度20m构成,办公楼的整体高度为80m,占地总面积为13000m2,一层作为地下室使用,该地下室的深度为6m。以钢筋混凝土作为办公楼的框架材料,而基础结构则利用沉管灌注柱;办公楼的每层洗手间和厨房都采用防滑地板砖,而办公楼的日常营业楼层、会议室楼层的地面则采用花岗岩地板;每一楼层的洗手间和厨房墙壁采用瓷砖墙面,其余内墙壁则采用乳胶漆墙面;所有楼层屋顶采用铝合金材料进行吊顶;十四层办公楼采用铝合金材质的窗户,采用木门,外墙壁采用玻璃幕墙和铝合金墙;单人居住楼房的外墙壁采用贴面砖,贴地板砖前要腾空板面。
以上是该办公楼的设计和施工要求,在该工程施工的过程中可以从以下几方面做好质量控制工作。
2对施工过程中的工作人员的质量控制
工作人员是工程施工过程中的主体因素和最关键因素,而工作人员的综合素质和专业技能的高低直接影响着施工的质量。因此,对施工阶段的质量控制最关键的就是对施工人员的质量控制。
2.1创建一支具有专业技能的施工队伍
施工部门要对施工人员进行定期的专业培训,提高他们的综合素质、专业技能以及施工经验,且对上岗人员进行综合技能的考核,只有达到施工标准的工作人员才可以加入施工的队伍。
2.2培养一支高素质的监督和管理队伍
企业要根据工程项目的具体要求,选择综合素质较高的监督人员和管理人员,选择的监督人员和管理人员在具备高素质的同时还要具备相关的专业技能,可以选择工作经验丰富的员工,以便在施工现场对施工过程进行适当的指导。
2.3对施工人员进行考核,达标方可上任
对确定的进厂的监督人员、管理人员和施工人员进行综合素质及专业技能的考核,可以现场进行演示测试,清楚地了解每个员工的综合素质、技能水平和工作经验情况,以此来明确工作人员能否胜任。
3对施工过程中所需原材料的质量控制
3.1对原材料的采购进行合理的规划
施工部门所采用的原材料,既要符合施工的要求,又要保证材料自身的性能,在材料的采购过程中要根据施工图纸选择优质、完好的原材料。同时,在采购原材料时,一定要保证材料供应商提供质量证明书和产品合格证,以确保材料的实用质量。对于一些容易褪色、有色差的原材料,如地板砖、瓷砖等,在采购前一定要对材料用量做好准确的预算,尽量一次性采购齐全,防止因为材料不足再次采购时出现色差、质地不同等问题。
3.2对进厂后的原材料进行严格的审查
为了保证原材料进厂后的质量和数量,可以从以下几方面着手:
(1)按照施工的相关要求,要保证原材料的相关质量证明以及采购数量列表的存在,对要进厂的原材料进行抽样检查和复查,以确保原材料的质量满足规范要求,只有检查合格的原材料才可以进厂保存,以备使用。对于质量不过关的原材料,不可以验收,此时,应该要求材料供应商给予退货或换货解决。
(2)对于一些特殊材料,例如:钢筋、水泥、涂料、砖等,供应商除了要提供相关的质量证明和产品合格证外,还需要在采购现场进行取样并由双方人员共同送到质检单位进行检测,只有材料符合标准后才可以进行施工使用。
(3)对于混凝土材料,在采购后要由材料供应商提供混凝土各种成分配比资料以及各种材料配比的检测单,只有各方面都符合施工要求后,才可以將混凝土材料送至施工现场使用。
3.3对合格后的原材料进行科学的保存
对于各方面检测都合格的产品,一般都需要存放一段时间后才送到施工现场使用,因此,材料进厂后要进行良好的保存。在原材料的搬运过程中要注意轻拿轻放,防止材料破损;不同的材料要进行各自的保存,不可以把不同的材料进行混堆保存,这样会使得一些材料之间因为发生化学反应而失去原本的功能甚至危及工作人员的生命安全;对于一些存放时间过长的材料,还要进行相应性能的检测,功能仍然没有改变的可以继续使用。
4对施工过程中施工工艺的质量控制
4.1对施工设计进行合理的规划
对于施工的设计方案要进行合理的规划,要考虑到施工过程中的各方面影响因素。包括:施工附近的环境、施工的特点、施工的要求、施工的工期、施工的工艺流程等。具体说来有以下几点:对项目施工的特点进行详细的分析,找出施工難点,并针对这些特点和难点,寻求科学、合理、有效的施工方法和解决问题的措施;把施工的质量放在第一位,完善施工质量管理制度和控制方式;对施工现场进行仔细的勘查,找出最适合施工的平面布局方式;弄清施工现场周边的人文环境和自然环境,提供安全、可靠的施工环境;根据工程项目的要求,对施工的工期和进度进行合理的规划。
4.2对施工工艺流程的质量控制
在工程项目的施工阶段,要对施工前期、施工中期、施工后期进行全程的质量监控和管理,以确保施工的整体质量。可以从以下几方面着手:
(1)对施工前期的质量控制。在工程项目施工前期,要对施工过程中所需要的人力资源、物力资源、施工设计方案、施工工艺等进行检查和确认,只有当各方面条件都准备充分后才可以进行施工。一旦发现有关问题,要上报并进行及时的处理,避免施工过程中因准备不充分或其它问题而影响施工的进度。
(2)对施工过程中的监督、管理控制。在工程项目施工过程中,相关负责人员和管理人员要对施工现场进行视察,查看施工人员的工作态度、施工的进度、施工的工艺、施工的材料、施工的环境和设备运行等情况,一定要确保施工符合国家相关规范要求和施工设计图纸的要求。如果发现操作错误,要及时提出并给予相应的指导。
(3)要对施工中的隐蔽工程进行重点检查。当某一隐蔽工程施工完毕后,首先监督施工人员进行自检查、交接检查,最后由专业的检查部门进行最终的检查、确定,呈交检查报告单,并进行相应的复检。如果检查不合格,施工人员就要进行返工再施工,只有检查符合标准后,才可以进行以后的施工工序。
(4)整个工程竣工后要对工程进行全面的检查和复查,确定满足相关规范后方可进行最后的验收工作。
5对施工过程中仪器和设备的质量控制
对工程项目施工过程中所用到的施工仪器、施工设备要进行仔细的分析和选用。根据施工现场及周边的环境、施工的进度要求、施工的工艺要求、施工图纸的要求、施工的特点和施工的期限等进行全面的考虑,同时还要考虑到所选用仪器或设备的性能指标、安装部位、灵活性、型号、成本、数量等是否达到了施工的要求,并对其进行综合的考虑,选择经济、实用、耐用、易操作的施工仪器和设备。在施工工程中,要对施工的仪器和设备进行定期的检查和维护,确保仪器或设备的正常运行,一旦发现设备出现问题,要及时进行检修或更换设备,以确保施工质量和施工进度。
6结束语
综上所述,所谓的工程施工阶段的质量控制,就是指施工部门为了保证施工的质量符合国家有关规范而对工程施工的过程实行的质量控制。在工程的施工过程中,采取合理、有效的质量控制措施不仅仅可以提高工程的施工进度,还可以提高施工的整体质量,使企业为自身创造更多的经济效益,为国家和人民创造更多的社会效益。
参考文献
[1]任诗敏.工程施工阶段质量控制的探讨[J].北京电力高等专科学校学报(自然科学版),2011(2).
[2]赵红梅.工程施工阶段质量控制研究[J].中国科技博览,2011(32).
[3]周 彤,窦新志.浅谈工程施工阶段质量控制的主要途径[J].世界家苑,2012(1).
[4]郝良友,李化伟,魏清政.浅谈给排水及采暖工程施工阶段质量控制[J].投资与合作,2012(4)
关键词:工程施工;质量控制;措施Abstract: The stage of construction project quality control is reasonable or not directly affects the entire project quality is good or bad, only to take the quality management and control measures of scientific, reasonable, effective, in order to ensure the construction quality and the construction progress of the whole project. Therefore, the construction of composite personnel departments or units must cultivate the high comprehensive quality, at the same time, the introduction of modern advanced construction technology and construction equipment, optimize the allocation of resources in accordance with the relevant requirements and construction, make rational use of human resources, material resources, the construction of the project early, middle, late construction construction quality management and control of the whole, to ensure construction quality, strive to obtain the maximum economic benefits, creating more social benefit for the country and people.
Keywords: engineering construction; quality control; measures
中图分类号:TU71
1具体工程举例
现以某一分别由一桩14层的办公楼和一桩12层的单人居住楼房两部分组成办公楼工程项目为例进行分析。
该办公楼的工程要求如下:办公楼的高度由建筑高度60m和顶层钢桅杆高度20m构成,办公楼的整体高度为80m,占地总面积为13000m2,一层作为地下室使用,该地下室的深度为6m。以钢筋混凝土作为办公楼的框架材料,而基础结构则利用沉管灌注柱;办公楼的每层洗手间和厨房都采用防滑地板砖,而办公楼的日常营业楼层、会议室楼层的地面则采用花岗岩地板;每一楼层的洗手间和厨房墙壁采用瓷砖墙面,其余内墙壁则采用乳胶漆墙面;所有楼层屋顶采用铝合金材料进行吊顶;十四层办公楼采用铝合金材质的窗户,采用木门,外墙壁采用玻璃幕墙和铝合金墙;单人居住楼房的外墙壁采用贴面砖,贴地板砖前要腾空板面。
以上是该办公楼的设计和施工要求,在该工程施工的过程中可以从以下几方面做好质量控制工作。
2对施工过程中的工作人员的质量控制
工作人员是工程施工过程中的主体因素和最关键因素,而工作人员的综合素质和专业技能的高低直接影响着施工的质量。因此,对施工阶段的质量控制最关键的就是对施工人员的质量控制。
2.1创建一支具有专业技能的施工队伍
施工部门要对施工人员进行定期的专业培训,提高他们的综合素质、专业技能以及施工经验,且对上岗人员进行综合技能的考核,只有达到施工标准的工作人员才可以加入施工的队伍。
2.2培养一支高素质的监督和管理队伍
企业要根据工程项目的具体要求,选择综合素质较高的监督人员和管理人员,选择的监督人员和管理人员在具备高素质的同时还要具备相关的专业技能,可以选择工作经验丰富的员工,以便在施工现场对施工过程进行适当的指导。
2.3对施工人员进行考核,达标方可上任
对确定的进厂的监督人员、管理人员和施工人员进行综合素质及专业技能的考核,可以现场进行演示测试,清楚地了解每个员工的综合素质、技能水平和工作经验情况,以此来明确工作人员能否胜任。
3对施工过程中所需原材料的质量控制
3.1对原材料的采购进行合理的规划
施工部门所采用的原材料,既要符合施工的要求,又要保证材料自身的性能,在材料的采购过程中要根据施工图纸选择优质、完好的原材料。同时,在采购原材料时,一定要保证材料供应商提供质量证明书和产品合格证,以确保材料的实用质量。对于一些容易褪色、有色差的原材料,如地板砖、瓷砖等,在采购前一定要对材料用量做好准确的预算,尽量一次性采购齐全,防止因为材料不足再次采购时出现色差、质地不同等问题。
3.2对进厂后的原材料进行严格的审查
为了保证原材料进厂后的质量和数量,可以从以下几方面着手:
(1)按照施工的相关要求,要保证原材料的相关质量证明以及采购数量列表的存在,对要进厂的原材料进行抽样检查和复查,以确保原材料的质量满足规范要求,只有检查合格的原材料才可以进厂保存,以备使用。对于质量不过关的原材料,不可以验收,此时,应该要求材料供应商给予退货或换货解决。
(2)对于一些特殊材料,例如:钢筋、水泥、涂料、砖等,供应商除了要提供相关的质量证明和产品合格证外,还需要在采购现场进行取样并由双方人员共同送到质检单位进行检测,只有材料符合标准后才可以进行施工使用。
(3)对于混凝土材料,在采购后要由材料供应商提供混凝土各种成分配比资料以及各种材料配比的检测单,只有各方面都符合施工要求后,才可以將混凝土材料送至施工现场使用。
3.3对合格后的原材料进行科学的保存
对于各方面检测都合格的产品,一般都需要存放一段时间后才送到施工现场使用,因此,材料进厂后要进行良好的保存。在原材料的搬运过程中要注意轻拿轻放,防止材料破损;不同的材料要进行各自的保存,不可以把不同的材料进行混堆保存,这样会使得一些材料之间因为发生化学反应而失去原本的功能甚至危及工作人员的生命安全;对于一些存放时间过长的材料,还要进行相应性能的检测,功能仍然没有改变的可以继续使用。
4对施工过程中施工工艺的质量控制
4.1对施工设计进行合理的规划
对于施工的设计方案要进行合理的规划,要考虑到施工过程中的各方面影响因素。包括:施工附近的环境、施工的特点、施工的要求、施工的工期、施工的工艺流程等。具体说来有以下几点:对项目施工的特点进行详细的分析,找出施工難点,并针对这些特点和难点,寻求科学、合理、有效的施工方法和解决问题的措施;把施工的质量放在第一位,完善施工质量管理制度和控制方式;对施工现场进行仔细的勘查,找出最适合施工的平面布局方式;弄清施工现场周边的人文环境和自然环境,提供安全、可靠的施工环境;根据工程项目的要求,对施工的工期和进度进行合理的规划。
4.2对施工工艺流程的质量控制
在工程项目的施工阶段,要对施工前期、施工中期、施工后期进行全程的质量监控和管理,以确保施工的整体质量。可以从以下几方面着手:
(1)对施工前期的质量控制。在工程项目施工前期,要对施工过程中所需要的人力资源、物力资源、施工设计方案、施工工艺等进行检查和确认,只有当各方面条件都准备充分后才可以进行施工。一旦发现有关问题,要上报并进行及时的处理,避免施工过程中因准备不充分或其它问题而影响施工的进度。
(2)对施工过程中的监督、管理控制。在工程项目施工过程中,相关负责人员和管理人员要对施工现场进行视察,查看施工人员的工作态度、施工的进度、施工的工艺、施工的材料、施工的环境和设备运行等情况,一定要确保施工符合国家相关规范要求和施工设计图纸的要求。如果发现操作错误,要及时提出并给予相应的指导。
(3)要对施工中的隐蔽工程进行重点检查。当某一隐蔽工程施工完毕后,首先监督施工人员进行自检查、交接检查,最后由专业的检查部门进行最终的检查、确定,呈交检查报告单,并进行相应的复检。如果检查不合格,施工人员就要进行返工再施工,只有检查符合标准后,才可以进行以后的施工工序。
(4)整个工程竣工后要对工程进行全面的检查和复查,确定满足相关规范后方可进行最后的验收工作。
5对施工过程中仪器和设备的质量控制
对工程项目施工过程中所用到的施工仪器、施工设备要进行仔细的分析和选用。根据施工现场及周边的环境、施工的进度要求、施工的工艺要求、施工图纸的要求、施工的特点和施工的期限等进行全面的考虑,同时还要考虑到所选用仪器或设备的性能指标、安装部位、灵活性、型号、成本、数量等是否达到了施工的要求,并对其进行综合的考虑,选择经济、实用、耐用、易操作的施工仪器和设备。在施工工程中,要对施工的仪器和设备进行定期的检查和维护,确保仪器或设备的正常运行,一旦发现设备出现问题,要及时进行检修或更换设备,以确保施工质量和施工进度。
6结束语
综上所述,所谓的工程施工阶段的质量控制,就是指施工部门为了保证施工的质量符合国家有关规范而对工程施工的过程实行的质量控制。在工程的施工过程中,采取合理、有效的质量控制措施不仅仅可以提高工程的施工进度,还可以提高施工的整体质量,使企业为自身创造更多的经济效益,为国家和人民创造更多的社会效益。