泰州市自来水公司第二水厂在原产5万吨/日的基础上,再扩建5万吨/日供水工程,是泰州市人民政府的重点工程。该工程从1997年3月破土动工,至1998年7月投产运行,历时一年零四个月。由于自来水公司对这项工程坚待两手抓,实行全方位、全过程的控制管理,不仅提前半年完成工程,而且使这个计划总投资3650万元的工程,在增加约214万元工程量的情况下,非但使增加的工程量全部自行
Taizhou Water Supply Company’s No. 2 Water Plant has expanded its 50,000-ton-per-day water supply project on the basis of 50,000 tons/day of production. It is a key project of the Taizhou Municipal People’s Government. The project broke ground in March 1997 and went into operation in July 1998. It lasted one year and four months. As the water supply company has to stay abreast of this project and implement all-round, full-process control and management, not only completing the project half a year in advance, but also making the project a total investment of 36.5 million yuan, an increase of about 2.14 million yuan in the amount of work Next, not only increase the amount of additional work on its own