镇江大港深水码头设计采用φ1200毫米大型钢管桩基础,桩的现场测试工作业已在1982年6月8日开始,年内全部试桩工作(包括测试数据的分析)即可完成。这次试桩的规模较大,预估需耗用资金109万元。测试的项目包括打桩的动方测试、波动方程参数测定、垂直静载试验和水平荷载试验等;测试的仪器采用了大位移计、应变杆、加速度计、土压力盒等。根据初步获得的测试数据分析,在该地区的地质条件下,长
Zhenjiang Dagang Deepwater Pier design using φ1200 mm large steel pipe pile foundation, pile site test work has been in June 8, 1982 began the year all the pile test work (including the test data analysis) can be completed. The larger test piles, the estimated cost of 1.09 million yuan of funds needed. The test items include the dynamic test of piling, the determination of wave equation parameters, vertical static load test and horizontal load test; the instrument used in the test is a large displacement meter, strain gauge, accelerometer, earth pressure box and so on. According to preliminary analysis of the test data obtained, the geological conditions in the area are long