天津北疆一期2×1000MW机组工程安装了6台型号为MPS275辊盘式中速磨煤机,该磨煤机与300、600MW机组中速磨煤机相比结构有一定的变化,而且体积和单件质量较大,在运输、安装中易出现变形,造成组合、安装中出现较大误差。在施工现场采取了基础台板变形和下架体偏差的控制,喷嘴环间隙和分离器施工方案的调整等措施,很好地解决了工程中出现的问题,顺利完成了磨煤机的安装施工任务。
6 sets of MPS275 roller disc medium speed coal mills were installed in the 2 × 1000MW unit project of the first phase of Tianjin Beijiang. The structure of the mill has a certain change compared with that of 300,600MW medium speed coal mills, and the volume And a single piece of larger quality, easy to appear in the transport, installation deformation, resulting in a combination of large errors in the installation. In the construction site to take the basis of the deformation of the deck and the next frame body deviation control, nozzle ring gap and separator construction program adjustments and other measures to solve the problems in the project, the smooth completion of the installation of coal mill construction task.