英国于1977年起执行的“猎迷”MR.3空中预警机计划,原定从1984年起皇家空军可获得十一架这种飞机,供远程警戒和空中截获指挥用。当时估计总费用为3.75亿美元。现知实现此项计划的费用将超出25亿美元。研制电子设备的延误将推迟使用期2~5年。事实上,1988年以前,11架飞机不可能全部和同时运转。最新消息说,英国国防部可能考虑于1986年使用一小部分只具有有限作战能力的“猎迷”Mk.3。负责航空电子设备研制的英国通用电气公司(GEC)航空电子设备部将继续努力工作,但追加费用的资金来
Britain’s “Hunter” MR.3 airborne early warning aircraft program, implemented in 1977, was originally scheduled to fly the RAF 11 aircraft from 1984 onwards for long-range alert and air interception command. The total estimated cost was $ 375 million at the time. It is now known that the cost of implementing this plan will exceed 2.5 billion U.S. dollars. Delay in the development of electronic equipment will be delayed for 2 to 5 years. In fact, it is not possible to operate all 11 aircraft simultaneously and simultaneously until 1988. According to the latest news, the British Ministry of Defense may consider using a small part of “Hunter Mk.3” with limited operational capabilities in 1986. The United Kingdom’s General Electric Company (GEC) Avionics Division, which is responsible for the development of avionics, will continue to work hard, but with additional costs to fund