由联合企业Nishimatsu Kumagai建设的穿越香港西部港口的沉管隧道进展迅速,缩短了原计划安排的时间,预计于明年3月可完工,比计划提前3个月结束。 最后一节沉管已成功地下放到海底的确切位置上。隧道总长1363m,由12节预制管段组成,每节重35000吨,长113m,宽33.5m,高8.8m。管段在Sheko一专用干坞中批量生产。每
Immersed tunnels crossing the western port of Hong Kong built by the joint venture Nishimatsu Kumagai have progressed rapidly, shortening the original planned timetable and are expected to be completed by March next year, three months ahead of schedule. The last section of immersion tube has been successfully released to the exact position of the seafloor. The total length of the tunnel is 1363m, which is composed of 12 prefabricated pipe sections with a weight of 35,000 tons and a length of 113m, a width of 33.5m and a height of 8.8m. Pipe sections are mass-produced in Sheko’s dedicated dry dock. each