丹江口水利枢纽的施工导流采用分期的围堰方式。1959年初,第一期右岸低围堰建成。在59年汛期,洪水由左岸束狭部分河道下洩,在围堰内进行大坝基础及导流部分的施工。至59年末,右岸导流部分将完成,再在左岸进行截流,修建第二期左岸高围堰,继续进行左岸大坝的施工。60年汛期,洪水即由右岸导流部分下洩。第二期围堰的规模是很大的。据初步估计,顶高将达120—125米高程(吴淞基面,下同),已初步形成水库,库容有20余亿立方米。上游围堰的高度,将近40—50米。一旦失事,其后果是异常严重的。因此,初步决定围堰应按1%洪水设计,0.5%洪水校核。
Danjiangkou Water Control Project construction diversion by staging cofferdam. In early 1959, the first phase of the right bank built a low cofferdam. In the 59-year flood season, floods were discharged from narrow bunds on the left bank to carry out construction of the dam foundation and the diversion section within the cofferdam. By the end of 59, the diversion of the right bank will be completed, then the left bank will be closed for the construction of the second bank of high left bank cofferdam and the construction of the left bank dam will continue. In the 60-year flood season, floods were partially discharged from the diversion on the right bank. The size of the second cofferdam is great. According to preliminary estimates, the top will reach 120-125 meters elevation (Wusong basal plane, the same below), has initially formed a reservoir, storage capacity of more than 20 billion cubic meters. The height of the upstream cofferdam, nearly 40-50 meters. Once the accident, the consequences are unusually serious. Therefore, the preliminary decision cofferdam should be 1% of the flood design, 0.5% flood check.