辽宁SQ水泥有限公司余热发电项目系改造工程由我公司总承包,于2011年9月左右正式投运。2012年4月,SP炉省煤器漏水,漏点集中在省煤器的最下一级。经过多次维修均未彻底解决泄漏问题。为避免同类事故再次发生,保证锅炉安全经济运行,我们对省煤器泄漏失效的原因进行具体分析,并提出相应的处理措施。
Liaoning SQ Cement Co., Ltd. waste heat power generation project renovation project by my company general contracting, officially put into operation in September 2011 about. April 2012, SP furnace economizer leaks, leaks concentrated in the lowest level economizer. After many repairs are not completely solve the problem of leakage. In order to avoid the recurrence of similar accidents and ensure the safe and economic operation of boilers, we analyzed the causes of the failure of economizer leakage and put forward the corresponding measures.