刘家峡水电站四号机定子系在安装间组合成整体,经过下线、耐压后与上机架、推力轴承一起吊入机坑安装就位的。由于安装场地的限制,定子组装场地只能布置在转子组装场地的右侧,而四号机坑却在转子组装场地的左侧。正式安装时,就必须先吊转子,后吊定子,用定子套转子。由于二者之间仅有27毫米的空气隙,这就要求定子吊起后必须有良好的水平度,吊装难度较大。
Liujiaxia hydropower station on the 4th machine stator assembly in the installation of the combination between the whole, after the next line, after the pressure with the rack, thrust bearing hanging into the machine pit installed in place. Due to the installation site restrictions, the stator assembly site can only be arranged on the right side of the rotor assembly site, while the fourth machine pit is on the left side of the rotor assembly site. Formal installation, you must first hang the rotor, after hanging stator, stator sleeve rotor. Since only 27 mm air gap between the two, which requires the stator must have a good level after lifting, lifting more difficult.