(一) 第二季度新产品新式38公斤重轨的生产,平均小时产量超过了计划指标,5月份实际比计划平均提高1.3%;6月份实际比计划平均提高10.7%;而作业率却远远落在计划后面。第二季度实际平均有效作业率比计划低24.7%,因此5月份仅完成产量计划的80.76%,6月份仅完成90.86%;如果作业率能按计划实现,不仅能够完成计划,而且可以超额。质量也未达到计划指标,实际平均合格率比计划低2.64,扣除计划内的二级品、次废品共达459吨。精整交库也不能做到及时,迄至6月底待验品还
(I) Production of the new 38 kg heavy rail for the new product in the second quarter, with an average hourly output exceeding the plan target, an actual increase of 1.3% over the plan in May; an actual increase of 10.7% over the plan in June; and a far lower operating rate Fall behind the plan. The actual average effective operating rate in the second quarter was 24.7% lower than the plan, so only 80.76% of the production plan was completed in May and only 90.86% in June. If the operating rate can be realized as planned, it can not only complete the plan but also allow it to surpass. The quality has not reached the plan index, the actual average pass rate is lower than the plan 2.64, deducting the planned second grade, sub-scrap totaling 459 tons. Satisfaction can also be done in a timely manner, until the end of June to be tested goods also