贝勒煤矿地质条件极其复杂,为了缩短工作面回撤与安装时间,将传统的装车搬运方式改为在自制滑道上直接拖运设备的方式,实现综采支架整体快速转运,节省进空车、装车、卸车、出空车工序所需时间,避免了原回撤与安装工艺中可能出现的跑车、掉道事故,有效地提高了作业的安全性,间接地提高了矿井的生产效益。
Belle coal mine geological conditions are extremely complicated. In order to shorten the work face retracement and installation time, the traditional loading and unloading method is changed to the way of hauling equipment directly on the self-made slideway to realize the overall rapid transport of the fully mechanized mining support, Loading, unloading, emptying process time required to avoid the original retractable and installation process may occur sports car, off the road, effectively improve the safety of operations, indirectly improve the production efficiency of the mine.