安康水电站是国家七五计划的重点建设工程。为了满足工地施工用水的需要,修建了一座能容纳1000吨生产用水的大型砼水池。总投资15万元,于1984年7月完工。由于设计等原因,装水时发现水池墙壁中部共有四条裂缝,每条裂缝长都在3米以上,不能装水使用,严重地影响大坝施工用水。有关单位采用环氧树脂及其它办法修补,但未
Ankang Hydropower Station is a national key project of the Seventh Five-Year Plan. In order to meet the construction site needs of water, built a large concrete tank can accommodate 1,000 tons of production water. A total investment of 150,000 yuan, completed in July 1984. Due to design and other reasons, it was found that there were four cracks in the middle of the pool wall when the water was filled. Each crack was longer than 3 meters and could not be filled with water, which seriously affected dam construction water. Relevant units using epoxy resin and other methods of repair, but not