9月19日10时4分,通过将新都桥T接点——220千伏甘孜变电站——110千伏石渠变电站相连接的输电线路,甘孜藏族自治州石渠县并入了大电网,这意味着“新甘石”联网工程圆满收官。“没来过石渠的人,不知道这里缺电的苦。石渠的冬天特别冷,每年最寒冷的10月到第二年的4月,这里基本上无电可用。”石渠县虾扎乡党委书记、乡长阿松说道。
At 1044 hours on September 19, Shiqu County in the Ganzi Tibetan Autonomous Prefecture was incorporated into a large power grid by connecting transmission lines connecting the Xinduqiao T-junction - the 220 kV Ganzi Substation - the 110 kV Shiqu Substation, which means “Xin Gan Shi ” networking project successfully ended. “People who have not been to the quarry do not know the power shortage here.” The quarry is especially cold in winter, and from the coldest October each year to the second year in April, there is basically no electricity available here. "Shiqu County Shrimp Township party secretary, Mayor Ason said.