案例回顾2010年3月,常州某建筑公司与常州某工具公司签订建设工程施工合同一份,合同约定由建筑公司承接工具公司的厂房工程,合同价款为188万元整,合同还约定了工期,仲裁等条款。合同签订后,建筑公司即按照工具公司提供的《地质报告》、《设计图纸》进行施工。在基础的施工过程中发现,地质单位提供的地质资料有误,而设计图纸也是套用民用设计的规范而非工业设计规范。如果按照设计图纸施工,
Case Review In March 2010, a construction company in Changzhou signed a construction contract with a tool company in Changzhou. The contract stipulates that the construction company will undertake the construction of the tool company with the contract price of 1.88 million yuan. The contract also stipulates the construction period, Arbitration and other terms. After signing the contract, the construction company shall follow the construction company’s “geological report” and “design drawings” provided by the tool company. Found in the basic construction process, geological units provided by the geological data is wrong, and design drawings is also applied civil design specifications rather than industrial design specifications. If you follow the design drawings construction,