一进10月,山东特高压工程建设就捷报频传:10月7日,榆横—潍坊1000千伏特高压交流线路工程第21标段基础灌注桩率先完成浇筑,比二级网络计划整整提前了3个月;10月9日,榆横—潍坊工程潍坊变电站接地网开始敷设,标志该站电气工程A包施工正式开始;10月10日,锡盟—山东1000千伏特高压交流工程济南变电站2号主变A相套管吊装顺利就位,标志该站第一台主变第一相安装取得圆满成功……
In October, Shandong UHV engineering reported on the fly: October 7, Yu-Heng - Weifang 1000 kV UHV AC Line project section twenty-first section of the basic pouring piles completed the first pouring than the secondary network plan a full 3 Month; October 9, Yu Heng - Weifang Weifang Substation grounding grid began laying, marking the station construction of electrical engineering A package officially began; October 10, Ximeng - Shandong 1000 kV UHV AC substation No. 2 Main transformer A-phase casing hoisting smoothly in place, marking the station’s first phase of the first phase of the installation of a complete success ......