湖南株洲某工程的爆扩桩基础的整个施工期间,正逢“四人帮”的严重干扰破坏,施工管理不严,打桩施工记录尚不能完全反映施工实际情况,工程质量有问题而又无法找出承载力有疑问的爆扩桩,故必须进行逐根检查。对一百多根爆扩桩要用静荷载试验进行逐根检查,是不现实的,也是不可能的,于是工程指挥部研究决定采用四川省建筑
During the entire construction period of the explosion-expanded pile foundation of a project in Zhuzhou, Hunan Province, the serious interference and destruction of the “Gang of Four” occurred, the construction management was not strict, and the construction record of piling could not fully reflect the actual construction conditions. There was a problem with the quality of the project and it was impossible to identify the bearing. The explosion-expansion piles in question have to be checked one by one. It is unrealistic and impractical to examine each of the more than one hundred explosion-expanded piles by static load tests, and the Engineering Command decided to adopt Sichuan Provincial Construction.