论文部分内容阅读
高层住宅施工中,垃圾道是一项既费工时又不易做好的项目。垃圾道在外墙外侧时,主要采用预制钢筋混凝土垃圾道和现浇钢筋混凝土垃圾道。我们公司在近年施工的高层住宅现浇钢筋混凝土垃圾道中多采用拔模施工方法,取得了较好的经济效益。一、模板设计垃圾道外围尺寸为900mmx900mm,混凝土壁厚为8cm,内部净尺寸为740mm,住宅楼层高为2.8m,主体完工后垃圾道每楼
In the construction of high-rise residential buildings, the rubbish road is a project that is both labor-intensive and difficult to do well. Garbage Road outside the outer wall, the main precast reinforced concrete refuse road and cast-in-place reinforced concrete refuse Road. Our company in recent years, construction of high-rise residential cast-in-place reinforced concrete refuse more use of construction methods, and achieved good economic returns. First, the template design Garbage Road, the outer dimensions of 900mmx900mm, concrete wall thickness of 8cm, the internal net size of 740mm, residential floor height of 2.8m, the main body of the garbage floor after completion of each floor