薄腹屋面梁广泛用于工业厂房建筑中,由于运输不便,多在现场制作。过去采用木模施工,既费工又费料。我们在15m跨薄腹梁制作中,采用现场砖地模工艺,只使用了少量木模板,降低了造价,且成模质量好。若采用早强剂,构件可在4d后起吊堆放。砖地模稍做修补即可重复使用。现将其施工工艺介绍如下: 1.抄平放线 (1)将场地整平,放线后将线内地面夯实。 (2)按薄腹梁实样放线:
Thin-walled roof beams are widely used in industrial plant buildings, and are often produced on-site due to inconvenience of transportation. In the past, the use of wood mold construction was both laborious and wasteful. In the production of a 15m-span thin-belly beam, we use the live brick floor mold process, using only a small amount of wood formwork, which reduces the cost, and the mold quality is good. If early strength agents are used, the components can be lifted after 4 days. Tiles can be re-used with minor repairs. The construction process is now described as follows: 1. Copy and level the line (1) Level the site, after the line is put, the ground in the line will be compacted. (2) Putting thin wire on the actual sample: