巴东三峡水泥厂的前身是一个年产7000吨水泥的小厂,通过1984年的搬迁扩建和以后的技术改造,实际生产能力已达到10万吨。但是,由于种种原因,经济效益仍然上不去,在1995年之前,企业8年生产,5年亏损。1996年,在学习邯钢经验的高潮中,该厂被确定为恩施自治州经贸委学习邯钢经验的试点企业,经过全厂员工11个月的奋力拼搏,终于赢得了丰硕的成果。至
The predecessor of Badong Sanxia Cement Factory is a small factory with an annual output of 7,000 tons of cement. Through the relocation and expansion of 1984 and subsequent technological transformation, the actual production capacity has reached 100,000 tons. However, due to various reasons, economic efficiency still can not go up. Before 1995, the company produced 8 years and lost 5 years. In 1996, during the climax of studying the experience of Handan Iron and Steel, the plant was identified as a pilot company of the Enshi Autonomous Prefecture Economic and Trade Committee to learn from the experience of Handan Iron and Steel. After 11 months of hard work, the whole plant employees have finally won fruitful results. to