邯宝1号3 200m3大型高炉2016年6月1日因主皮带断裂造成非计划休风34.5h,休风前炉况持续稳定顺行、炉缸活跃、炉温充足、各项经济指标较好。此次送风恢复过程中降低负荷、重视炉热水平、调整炉料结构,根据轻负荷料下达位置及炉内接受情况分3个阶段进行风量和氧量的恢复。同时通过炉温情况补充煤粉、快速用上高风温,提前做好出铁准备、合理安排炉前作业等,实现了炉况的快速恢复。
Handan 1 3 200m3 large blast furnace June 1, 2016 due to the main belt rupture caused by non-scheduled wind break 34.5h, before leaving the wind furnace conditions continued steady and steady, hearth active, adequate temperature, the various economic indicators better . The air supply recovery process to reduce the load, pay attention to the furnace heat level, adjust the charge structure, according to the light load of material delivered to the location and acceptance of the furnace divided into three stages of air volume and oxygen recovery. At the same time through the furnace temperature to replenish the pulverized coal, rapid use of high wind temperature, make iron preparation ahead of schedule, reasonable arrangements for furnace operations, etc., to achieve a rapid recovery of furnace conditions.