对钢屋架的拼装,目前国内大都采用在施工现场先搭设一平台,然后将两半榀屋架平卧放置在平台上,再进行组并的方法。这种拼装方法,占地面积大,需用很多枕木、钢轨和钢板,消耗大量人工和材料。因此它仅在厂房面积不大的情况下较适用,对于多柱距、大跨度的屋架拼装,就很不适宜了。六冶结构公司在舞钢轧钢厂工程,曾采用了一种立着拼装的施工方法,先后拼装了223榀36米跨距的钢屋架,技术经济效果很好,可省大量材料和劳动力,加快了拼装进度,保证了施工质量。屋架的立拼装,是将屋架按吊车行走的路线和吊车的回转半径所能达到的范围,立着就位排放。排放的方式视施工现场的具体情况而定。一般有两
For the assembly of steel roof trusses, most of the current domestic use of a platform at the construction site first, and then the two semi-truss truss lying flat on the platform, and then grouping method. This assembly method covers a large area and requires many sleepers, rails and steel plates, and consumes a lot of labor and materials. Therefore, it is only suitable if the plant area is not large. For multi-pillar, long-span truss assembly, it is very inappropriate. Liuye Structure Company had adopted a construction method erected for assembling at the Wugang Steel Rolling Mill Project. It has successively assembled a steel truss with a span of 223 inches and 36 meters. The technical and economic results are very good. It can save a large amount of materials and labor and speed up the process. The assembly progress has ensured the construction quality. The erection and rigging of the truss is the range that can be reached by the truss walking along the crane and the radius of gyration of the crane. The method of discharge depends on the specific conditions at the construction site. There are two generally