统筹法是一种为生产建设服务的数学方法,是系统工程用于科学管理的有效方法。在湖南柿竹园矿的井巷工程排队中,我们应用这种方法进行战略部署,选取最优方案,抓住主要矛盾,开展技术革新,使井巷建设工期的安排从57个月缩短到34个月。在浦市磷矿的施工中,应用统筹法和优选法选取合理的操作方法和工艺参数,最大限度地采用平行作业,取得了独头月进903米的好成绩。因此,使统筹法更好地服务于生产建设,是一个十分值得注意的问题。一、统筹法在井巷施工中的应用统筹法是一种科学选优的方法,既可用来搞较大规模的矿山建设,安排战略部署,
Co-ordination Act is a mathematical method for production and construction services, is an effective method of system engineering for scientific management. In line with the well lane project of Shizhuyuan Mine in Hunan, we applied this method to conduct strategic deployment, selected the optimal plan, grasped the major contradictions and carried out technological innovations, shortening the construction schedule of the wellways from 57 months to 34 Months. In the construction of Pushan Phosphate Mine, the method of ordination and optimization is adopted to select the reasonable operation method and process parameters, and the parallel operation is used to the maximum extent to obtain a good result of 903 meters of single-headed moon. Therefore, it is a very worthwhile issue to make overall planning serve the production and construction better. First, the co-ordination method in the construction of roadway application Overall planning is a scientific method of selecting the best, can be used to engage in larger-scale construction of the mine, to arrange strategic deployment,