柴河水库库底清障工作,是在按正常高水位108m淹没线内进行的,包括树木及其残余物清理和地面地形整理两项内容,施工进度安排主要考虑筑坝主体工程施工进度和库区内移民动迁进度两个因素。在施工时间内,共清除树木及残余物43892棵,房基桥涵34022m ̄3,填平沟渠坑19354m ̄3,路基、沙堆1722m ̄3,形成冰下大拉网作业网场22处,机船底拖网作业网场8处,定置张网网基5处,养鱼种库湾1处,总清理面积546ha。捕鱼290.7万kg,产值739万元,利税198万元。
Chaihe reservoir bottom cleansing work is carried out in the normal high water level of 108m submerged line, including the removal of trees and their residues and surface topography of the two contents of the construction schedule mainly consider dam construction progress and the main library Immigrants within the relocation progress of two factors. During the construction period, a total of 43,892 trees and residues were removed, and the foundation bridges and culverts numbered 34022m ~ 3, filled trench ditches of 19354m ~ 3, subgrade and sand piles of 1722m ~ 3, Bottom trawl network 8, set Zhang net base 5, fish breeding bay 1, the total clean-up area of 546ha. 2907000 kg of fishing, the output value of 7.39 million yuan, profits and taxes 1980000 yuan.