鉴于加筋土挡墙具有明显的优越性,我们在云南省田坝、后所两个矿区进行了几座挡墙的试验性设计和施工。试验性挡墙最高为8.3米,最长为82米。目前已峻工的加筋土挡墙的照片见照片一至照片四。为了取得更多的第一性资料,我院已组织对加筋土挡墙进行模型试验和现场原型的测试科研项目的研究工作,这将为今后加筋土挡墙的推广起积极作用。目前加筋土挡墙在我国还处于引进国外资料,进行初期试验研究的阶段。现在将上述几座加筋土挡墙在设计施工中的一些体会总结于下,文中错漏之处,请给予批评指正。
In view of the obvious superiority of the reinforced earth retaining wall, we conducted experimental design and construction of several retaining walls in the Tianba and Housuo mining areas in Yunnan Province. The experimental retaining wall has a maximum height of 8.3 meters and a maximum length of 82 meters. Photographs of the reinforced earth retaining walls that have been completed so far are shown in Photo 1 through Photo 4. In order to obtain more primary data, our institute has organized the research on model tests of reinforced earth retaining walls and field prototype test and research projects, which will play an active role in promoting the use of reinforced earth retaining walls in the future. At present, the reinforced earth retaining wall is still in the stage of introducing the foreign data and conducting initial experimental research. Now we will summarize some of the above-mentioned several reinforced earth retaining walls in the design and construction. In the text, please give criticism and correction.