论文部分内容阅读
一、铺贴工艺(表1) 二、注意事项 1.铺贴前应先选砖,以减少板块尺寸偏差和色差,并预排,把非整跨部位安排在非出入口和次要部位,公共场所重要走廊、厅堂不宜出现非整砖,可将非整砖对称安排在两侧或周边,采用颜色较深的镶边板块代替非整砖;走廊与房间宜用另一颜色的板块在门口部位分隔,各自排板。 2.为预防因温差、干缩引发大面积脱层隆起,板块面层应从基层开始,宜12m左右沿柱网轴线设置分格缝,缝宽10~15mm,内填弹性嵌缝材料。
First, the paving process (Table 1) Second, the matters needing attention 1. Paving should be selected before the brick, in order to reduce the plate size deviation and color, and pre-discharge, the non-integration of the cross-sites in non-import and export of the site, public The important corridors and halls of the site should not be full of non-complete bricks. Non-entire bricks can be arranged symmetrically on both sides or in the periphery. Darker colored flanges can be used instead of non-solid bricks. Corridors and rooms should use another colored plate at the entrance. Separated, each row board. 2. In order to prevent the large area of delamination and bulging caused by temperature difference and dry shrinkage, the surface layer of the plate should start from the base layer. It is advisable to set sub-grid seams along the axis of the column net about 12m, the seam width is 10-15mm, and the elastic caulking material is filled in.