对于秦皇岛港一期煤码头工艺装卸设备安装,我们在吸取北仑港工程的经验基础上,根据国产工艺设备的具体情况和秦皇岛港的实际地理,气象条件,制定了码头工艺装卸设备安装以汽车吊为主,浮吊为铺,散件平地组焊、铆,整体吊装,保证了设备质量,加快了工程进度。整个工程“11大机1条线”(线指皮带
Based on the experience of Beilun Port project, based on the actual conditions of domestic craft equipment and the actual geographical and meteorological conditions of Qinhuangdao Port, we have set up the process of loading and unloading of the terminal craft loading and unloading equipment with a car crane Mainly, floating for the shop, spare parts flat welding, riveting, the overall hoisting, to ensure the quality of equipment and speed up the progress of the project. The entire project “11 large machine 1 line” (line refers to the belt