一、工程概况12号和14号两幢十六层公寓均为装配整体式钢筋混凝土双向框架结构。其主体结构部分是在建外工程指挥部统一领导,各兄弟单位紧密配合下,由我公司第一施工处担负构件吊装和运输任务。第一施工处广大职工在批林整风运动的推动下,鼓足干劲,坚持三结合,不断总结经验,改进施工方法,这两栋建筑分别于1973年2、4月份开始主体结构吊装,到5、7月份就顺利完成。十六层公寓按结构层数计,地下有2
I. Project Overview The two 16-storey apartments on the 12th and 14th are all assembled reinforced concrete two-way frame structures. The main part of the structure is under the unified leadership of the external construction project headquarters. Under the close cooperation of the fraternal units, the first construction department of our company is responsible for the lifting and transportation of the components. In the first construction department, the majority of employees, driven by the approval of the forestry rectification movement, worked hard, adhered to the three combinations, continuously summed up experience, and improved the construction methods. The two buildings began lifting the main structure in February and April 1973 respectively. In July, it was successfully completed. 16-storey apartment in structural layers, 2 underground