天津市红旗路7000吨冷库是我工区无产阶级文化大革命以来第一个继续应用统筹方法组织施工的工程。这个工程由主库(包括电梯间)、凉肉间、群房(制冰间、磅间等)、汽车站台和火车站台等五个部分组成,共计16,420米~2。主库(包括地下室)是五层钢筋混凝土无梁楼盖,顶部是预应力大型屋面板。柱网6×6米,建筑物总高22.56米。造价267万元。装修比较复杂,一道保温墙有7~12道工序,地面做法有的多达13道工序。若按横道图的方式编制流水作业计划,工期需要二年多。我们学习了毛主席的
The 7,000 tons of cold storage at Hongqi Road in Tianjin was the first project that continued to use the method of organization and construction since the proletarian cultural revolution in our work area. This project consists of five parts, the main library (including elevators), cool meat room, group rooms (ice rooms, pounds, etc.), bus platforms, and train station platforms, for a total of 16,420 meters~2. The main storehouse (including the basement) is a five-story reinforced concrete beamless floor and the top is a prestressed large roof. The column net is 6 x 6 meters and the total height of the building is 22.56 meters. The cost was 2.67 million yuan. The decoration is more complicated. There are 7 to 12 thermal insulation walls, and some of the ground practices are as many as 13 procedures. If the flow plan is compiled in the form of a bar chart, the construction period will take more than two years. We have studied Chairman Mao’s