一、概况贵州体育馆主体建筑——比赛馆是一座外形复杂,前高后低的大跨度建筑,占地面积为5609m~2,建筑面积为10178m~2,可容纳5448人座。屋面由54m跨、倒三角变截面立体桁架承载,桁架共11榀,单榀最重达15t。比赛馆前面是地下停车库,左侧是接待楼群,右侧是练习馆,馆后左侧是待平小山头,馆后右侧是11榀桁架的制作现场和总拼装台(见图1)。二、方案选择和风险性预测根据现场实际情况、工期要求、质量要求、吊装安全性、现有设备能力、经济性以及“挖、革、改”精神等七个方面的因素,
I. Overview The main building of Guizhou Gymnasium - The competition hall is a large-span building with complex appearance and high front and low front. It covers an area of 5609m2 and a building area of 10178m2, accommodating 5448 seats. Roof by the 54m cross, inverted triangular cross-section truss truss, truss a total of 11 榀, a single 榀 up to 15t. In front of the competition hall is an underground parking garage. On the left is the reception building complex. On the right is the practice hall. The left side of the hall is to be covered with small hills. The right side of the hall is the production site of the 11th truss and the total assembly station ). Second, the program options and risk prediction According to the actual situation on the scene, the requirements of the construction period, quality requirements, lifting safety, the existing equipment capacity, economy and the spirit of “digging, leather, change” and other seven aspects,