在水电站厂房结构中,尾水管上弯段是体形最复杂、施工最困难的部位。以往均采用满堂脚手木支撑,进行现场浇筑混凝土。这样,一台大型机组的尾水管就需用木材约125米~3,消耗量很大。为了节约木材,在三门峡水电站建设中,曾将木支撑及模板改用砌砖,这样虽可以节约木材,但用砖量相当大,每台机组需用砖约12万块,其损耗率达70%,而且占用堆放场地较大,拆、砌砖所用工期也较长。
In the plant structure of the hydropower station, the curved section on the draft tube is the most complex shape and the most difficult part of the construction. In the past, full supportive scaffolding was used to cast concrete on site. In this way, the draft tube of a large unit needs about 125 m ~ 3 of wood, which consumes a lot. In order to save timber, in Sanmenxia hydropower station construction, once the wood support and template to brick, although this can save wood, but the amount of brick is quite large, each unit requires about 120,000 bricks, the loss rate of 70 %, But also occupy a larger stacking site, demolition, brickwork is also a longer duration.