2014年8月29日下午,攀钢钒炼钢厂方坯连铸作业区精整乙班班长王宗佩在3号方圆坯连铸机堆场清点铸坯,准备将160mm×160mm断面的铸坯装车外发。今年,炼钢厂对3号方圆坯连铸机实施新增断面技改,在原有2个断面的基础上,新增160 mm×160 mm断面,使铸坯断面规格从2个增加到3个。炼钢厂采取超常规措施,仅用38天完成了常规情况下需要半年时间才能完成的工程,于6月28日竣工投产。
On the afternoon of August 29, 2014, Wang Zongpei, a class leader of finishing class B in the continuous casting operation area of the billet continuous casting of vanadium steelmaking plant in Panzhihua Iron and Steel Group, counted the billets in the yard of round billet caster No. 3 and prepared the billets of 160mm × 160mm section Out of the car. This year, the steel mill on the 3rd round billet caster implementation of the new section of technical transformation, in the original two sections, based on the new 160 mm × 160 mm section, the slab section specifications from 2 to 3 . The steel mill took unconventional measures to complete the project that normally took half a year to complete in only 38 days and was completed and put into operation on June 28.