八钢1号COREX炉迁建工程建设现场,COREX炉工程主体——出铁场塔架基础钢结构已安装至46米,主控楼主体完工,两台主变压器已完成安装。与COREX炉工程主体钢结构同时进行的气化炉钢结构已安装到第12带,剩下的第13至17带均已在地面焊接完毕,近期就能安装到位。与COREX炉工程主体相临的冷煤气加压站,其主要设备大部分也已安装完毕,外墙封闭工作将很快开始。
The construction of the relocation project of Bayi No.1 COREX furnace was completed. The main steel structure of the COREX furnace project - the steel structure of the tower base of the tipping yard was installed to 46 meters. The main control building was completed and the two main transformers had been installed. The gasifier steel structure with the main steel structure of the COREX furnace has been installed to the twelfth belt. The remaining belts 13 to 17 have been welded on the ground and can be installed in place in the near future. Cold gas station adjacent to the main COREX furnace project, most of its major equipment has also been installed, the external wall closure will begin soon.