常规的转子轮毂与发电机主轴热套施工方案主要有两种:轮毂套轴方案和轴插轮毂方案,两种方案根据工程现场实际情况进行选用。雷打滩水电站因安装场垂直空间限制,并考虑工程实际特点和经济安全性,对两种施工方案进行了比选,最终采取了轴插轮毂方案。实践表明,采用轴插轮毂方案有效缩短了工期并降低了费用,可供其他类似工程参考和借鉴。
Conventional rotor hub and generator spindle heat sleeve construction program there are two main types: hub sleeve shaft and wheel hub program, two programs based on the actual situation of the project site selection. Due to the vertical space limitation of the installation site, and taking into account the actual project characteristics and economic security, the three projects were compared and selected, and finally the hub-and-spoke hub program was adopted. Practice shows that the use of shaft insert hub program effectively shorten the construction period and reduce costs for other similar projects for reference and reference.