The real-time informational monitoring system is adopted in the construction of middle tower foundation of Taizhou Bridge for the first time. The geometric stat
Taizhou Bridge is a highway three-pylon two-span bridge with span arrangement of 1 080 m + 1 080 m and the length of the main cable is more than 3 100 m. It is