滑模施工垂直度控制是施工中重要环节。近年来除采用激光铅直仪等先进方法进行控制外,施工中采用导电线锤装置同样具有明显效果,该方法简单易行,可随时将偏差情况通过信号装置反映到液压控制台上,即随时采取纠正措施、施工中具体做法如下: 施工前在构筑物地面指定部位设立标点,在标点上安设触点盘装置,触点盘分别设八个或四个方位触点,各触点分别有导线连通
Slipform construction verticality control is an important part of construction. In recent years, in addition to advanced methods such as laser plumbago metering, the use of a conductive hammer device in construction has also had a significant effect. This method is simple and easy to implement, and the deviation can be reflected on the hydraulic control console at any time through the signal device. The corrective measures and specific methods in construction are as follows: Before the construction, punctuation points shall be set up on designated sites on the surface of the structure, and a contact disk device shall be installed on the punctuation points. Contact plates shall be provided with eight or four azimuth contacts respectively. Each contact has a wire. Connectivity