本文从工作实际出发,探讨了EPC总承包背景下火电工程设备竣工文件的全程管理方法和模式。详细介绍了全程管理模式的合同签订、程序宣贯、确定范围、电子版预检、出厂验收、开箱检验、现场验收、跟踪评分8项环节,并重点分析了全程管理模式需出台合理科学的指导文件,以及总包方各部门的通力配合。一、概述设备竣工文件主要包括设备厂家提供的文件和在设备安装、调试中形成的文件两大部分,具体包括设备
In this paper, starting from the actual work, this paper explores the whole management method and mode of the completion documents of the thermal power engineering equipment under EPC general contracting background. This paper introduces in detail eight aspects of contract signing, procedure declaration, scope determination, pre-inspection of electronic version, factory acceptance, unpacking inspection, on-site acceptance and tracking of the whole management mode, and focuses on analyzing the whole management mode to introduce a reasonable and scientific Guidance documents, as well as all the parties involved in the overall package. I. Overview The equipment completion documents mainly include the documents provided by the equipment manufacturers and the two parts of the documents formed during the equipment installation and debugging, including the equipment