齐鲁氯碱厂新建聚氯乙烯装置在投入运行之初,采用了磁力耦合器和自耦变压器作为降压起动设备,但在运行期间多次出现故障,严重影响生产,经过考察论证陆续更换成开关变压器软起动装置作为降压起动设备,自投入运行以来,安全稳定,未出现影响生产事故。本文介绍了开关变压工作原理、组成和特点,阐述了开关变压器软起动装置在我厂应用的原因,着重讲了开关变压器软起动装置一拖二控制方式的具体接线,组成原件,例举了软起动装置在投入运行期间出现的故障及处理,阐明了软起动装置故障率低,且故障信息一目了然,使运行值班人员能快速准确的处理故障。
New PVC plant in Qilu chlor-alkali plant put into operation at the beginning of the use of magnetic coupling and autotransformer as a step-down starting equipment, but many times during operation failure, seriously affecting the production, after a series of investigation and verification successively replaced by the switch transformer Soft start device as a step-down starting equipment, put into operation since the safe and stable, did not affect the production accident. This paper introduces the working principle, composition and characteristics of the switch transformer, describes the reasons for the application of the switch transformer soft-start device in our factory, emphasizes on the specific connection of the switch transformer soft-start device one to two control mode, composed the original, Soft starter malfunction and handling during the operation, illustrates the soft starter low failure rate, and fault information at a glance, so that the duty on duty can quickly and accurately handle the fault.