我院为马钢设计的2500m~3高炉1号冲水渣系统工程于1994年4月与高炉同步投产。在水渣调试过程中,1号水渣系统首先投运,且调试顺利,一次投产成功.从国外引进的2号水渣系统经多次调试,最后参照1号系统,改进了投运中的间题,才逐渐投入正常运行。经过两年的生产实践,马钢对我院设计的1号水渣系统评价较高,认为1号系统的
Our hospital designed for the Masteel 2500m ~ 3 blast furnace slag flushing system on the 1st project in April 1994 with the blast furnace simultaneously put into operation. During the process of water slag debugging, water slag system No.1 was put into operation at first, and the commissioning was successful and a successful operation was put in. The water slag system No. 2 imported from abroad was debugged several times, and finally the system No. 1 was improved to put into operation Problems, it gradually put into normal operation. After two years of production practice, Masteel on the 1st of our hospital designed slag slag system is higher, that No. 1 system