论文部分内容阅读
这是狮子灘水电站工程中採用塊石混凝士的初步經驗,虽然还很不成熟,但已可看出它的巨大经济价值。在狮子灘工程中,1955年澆制大壩阻水牆13万多公方的塊石混凝土,即節省了7000多噸水泥和80多万元資金(包括水泥价值在内)。因此我们应当繼續研究改進塊石混凝土的应用和施工方法,並在適宜採用塊石混凝土的工程中推廣採用,以便为國家節省更多的資金。
This is the first experience of using limestone concrete in the Shizitan Hydropower Station project. Although it is still immature, it can be seen as a huge economic value. In the Lion Beach project, more than 13,000 square meters of block concrete were dug in 1955 to save more than 7,000 tons of cement and more than 800,000 yuan (including the value of cement). Therefore, we should continue to study the application and construction methods of improving block concrete, and popularize and adopt it in the project suitable for block concrete to save more funds for the country.