本钢5号高炉是2000m~3的大型高炉。1990年5月20日进行了第四代大修,1993年4月10日至5月13日进行了第四代第一次中修。投产后运行了近三年时间。在此期间,由于冷却水质、原料、操作、设备维护等方面因素的影响,致使高炉冷却设备、炉身下部钢甲损坏严重,严重威胁安全生产。于是在1996年4月2日至5月9日进行第四代第二次中修。根据逢修必改的原则,5号高炉第四代第二次中修主要技术改造内容如下。
Benxi Iron and Steel No. 5 blast furnace is 2000m ~ 3 large blast furnace. The fourth generation of overhaul was carried out on May 20, 1990, and the fourth generation of the first overhaul was carried out from April 10 to May 13, 1993. After operation for nearly three years. During this period, due to the influence of factors such as cooling water quality, raw materials, operation and equipment maintenance, etc., the steel plates in the blast furnace cooling equipment and the lower part of the furnace body were seriously damaged, which seriously threatened the safety in production. So in April 2, 1996 to May 9 for the fourth generation of the second repair. According to every principle must be changed, the fourth blast on the 5th of the fourth major technical renovation of the blast are as follows.