二期围堰由上游横向围堰和下游横向围堰组成,其中上横围堰长1375.94m,堰顶高程88.5m;下横围堰长1075.94m,堰顶高程81.5m。分为试验段、预进占段、河床段三个阶段施工。施工分水下抛填、陆上填筑、堰体风化沙振冲加密和防渗墙施工。预进占施工自1996年10月30日开始,至1997年7月初,累计完成土石方填筑194.58万m3,振冲加密5761m,平抛垫底84.64万m3,防渗墙成槽6500m2,达到了预期目标。
The second phase cofferdam consists of the upstream lateral cofferdam and the downstream lateral cofferdam, of which the upper cross cofferdam is 1375.94m in height and the weir crest elevation is 88.5m; the lower cross cofferdam is 1075.94m long and the crest elevation is 81.5m. Divided into the experimental section, pre-occupied section, riverbed construction in three stages. Sub-construction under the water throwing, landfill, Weir weathered sand Zhenchong encryption and cut-off wall construction. Pre-occupancy construction started from October 30, 1996 to early July 1997, accumulatively completed 1.4885 million cubic meters of earth and rock fill, vibration and vibration encryption 5761m, flat bottom of 846,400 m3, cut-off wall into a slot 6500m2, Achieved the desired goal.