三峡二期围堰预进占施工

来源 :中国三峡建设 | 被引量 : 0次 | 上传用户:weicengh
下载到本地 , 更方便阅读
声明 : 本文档内容版权归属内容提供方 , 如果您对本文有版权争议 , 可与客服联系进行内容授权或下架
论文部分内容阅读
二期围堰由上游横向围堰和下游横向围堰组成,其中上横围堰长1375.94m,堰顶高程88.5m;下横围堰长1075.94m,堰顶高程81.5m。分为试验段、预进占段、河床段三个阶段施工。施工分水下抛填、陆上填筑、堰体风化沙振冲加密和防渗墙施工。预进占施工自1996年10月30日开始,至1997年7月初,累计完成土石方填筑194.58万m3,振冲加密5761m,平抛垫底84.64万m3,防渗墙成槽6500m2,达到了预期目标。 The second phase cofferdam consists of the upstream lateral cofferdam and the downstream lateral cofferdam, of which the upper cross cofferdam is 1375.94m in height and the weir crest elevation is 88.5m; the lower cross cofferdam is 1075.94m long and the crest elevation is 81.5m. Divided into the experimental section, pre-occupied section, riverbed construction in three stages. Sub-construction under the water throwing, landfill, Weir weathered sand Zhenchong encryption and cut-off wall construction. Pre-occupancy construction started from October 30, 1996 to early July 1997, accumulatively completed 1.4885 million cubic meters of earth and rock fill, vibration and vibration encryption 5761m, flat bottom of 846,400 m3, cut-off wall into a slot 6500m2, Achieved the desired goal.
其他文献
党中央、国务院要求,从“九五”开始,要更加重视支持中西部地区经济的发展,逐步加大解决地区差距继续扩大趋势的力度,积极朝着缩小差距的方向努力。 我国西北五省区,土地面
黄河流经我国干旱缺水的西北和华北地区,供水的范围广,数量大。由于黄河本身水资源并不丰富,加上70年代特别是90年代以来黄河流域及下游引黄地区降雨量偏少、用水量又大量增
位于三峡左岸98.7m的混凝土拌和系统,装有日产强制式2×45001IHI楼。为确保混凝土拌和系统质量,曾进行过多项参教试验,在混凝土中既要掺粉煤灰,又要掺复合剂,还要接碎冰。为探索生
1 简 介全自动双波峰焊机是采用专利技术三相异步感应电磁泵作焊料发生器 ,为目前表面贴片混装线路板的高质量焊接要求而制造的富有独创设计的新一代焊接设备。该机能独立
隧洞工程与施工机械朱映译,贾葆珉校1概述隧洞开始施工时,要在充分考虑所开挖隧洞的地势、地形、地质、涌水、掘进方法等的同时,充分了解所选择的各种机械的性能后,来规划、设计选
海潮坝面板堆石坝在施工中调地制宜采用堆石料洞室爆破,级配符合设计要求。滑模用手动葫芦牵引,面板平整。对已成面板进行详细的检查,面板无贯穿性裂缝。工程进度快,质量优良。
近些年来,在汉语国际推广事业的不断发展壮大的大背景下,汉语国际教师的需求日益增加,汉语国际教育硕士专业随之应运而生。其培养目标是:“通过课程学习和教学实践,使学生具
在研究莫高窟地区地震地质条件及潜在地震危险性分析的基础上,基于地震的断层弹性位错理论,采用位移水平分布的抛物线模型,假定三危山断层分别发生5.5、6.0和6.5级地震情况下
国务院于1996年9月颁发了《关于“九五”期间深化科学技术体制改革的决定》,根据《决定》的要求,“九五”期间要初步建立起适应社会主义市场经济体制和科技自身发展规律的新
淮河从桐柏山蜿蜒东流约百余公里后,在河南省罗山县尤店乡李店村附近,汇纳了从南岸流来的一条河,这就是淮河上游的第一条支流——浉河。 浉河发源于河南和湖北两省交界、桐