由于在施工中强化了全面质量管理(TQC)工作,使水钢2号高炉(1200m~3)中修工程全面实现“保安全、质量好、工期短、不漏项”的目标,取得显著成绩。在施工中,除了建立工程质量保证体系、应用PDCA循环等方法外,还首先应用TQC新七种工具中的KJ法将施工全过程的众多工作绘制成A型图解,明确各部门责任和质量要求;绘制“大钟密合间隙不好”关联图,找出因果间的逻辑关系并采取对策措施保证了工程质量。TQC新七种工具有用图形、语言分析思想的特点,适用于大中型基建和检修工程,与其它工具联合使用能有效控制工序质量和工作质量。
As a result of strengthening TQC in construction, the repair project of No.2 BF at 1200m ~ 3 fully realized the goal of “ensuring safety, good quality, short construction period, no leakage” and achieved remarkable results . In the construction, in addition to the establishment of project quality assurance system, the application of PDCA cycle and other methods, but also the first application of the new TQC seven tools KJ law will be the whole process of construction of many of the work drawn into A-type diagram, a clear responsibility and quality requirements of various departments ; Draw the “big clock close gap with good” correlation diagram, find the logical relationship between causal and take countermeasures to ensure the quality of the project. TQC new seven kinds of tools useful graphics, language analysis of the characteristics of ideas for large and medium-sized infrastructure and maintenance projects, and other tools used in conjunction can effectively control the quality of work processes and quality.